    Project report

VDE 8.1 ABS 38 doubling of the track, Altmühldorf - Tüßling

PROJECT DESCRIPTION

The single track section Altmühldorf - Mühldorf - Tüßling as a central component of extension section 38 München Ost - Mühldorf - Freilassing - Border (ABS 38) is expanded to double track to expand the capacity. The line speed will be 160 km / h in the future. The following routes are affected by the reconstruction measures in the immediate vicinity of the Mühldorf am Inn railway station: 5700 Rosenheim - Landshut, 5600 München - Simbach and 5723 Mühldorf - Tüßling.

This "yellow construction site" is handled by various business divisions.

We also guarantee that we will implement this project according to our motto - experience the joy of construction!

FACTS AND FIGURES

Customer: DB ProjektBau GmbH, Munich
Main Construction period: 2013 – 2016
Employer: Südostbayernbahn (South-east Bavarian railway)
4.3 km section of track at the Mühldorf am Inn train station junction

CIVIL ENGINEERING

SERVICES

Excavation of soil and gravel 68,000 m3
Installation of PSS / FSS 35,000 m3
Installation of base gravel 5,600 m3
Manufacture of vibrated stone columns 1,000 m3
Soil stabilization by cutting in cement 5,000 m2
Seepage lines 5 km

EQUIPMENT USED

Drill
Rotary hoe
Chain dredger
Wheeled excavator
Crawlers
Wheel loaders
3 and 4-axle trucks
Rolling compactor

ASSIGNED STAFF

Average of 6 employees

IMPRESSIONS

TRACK CONSTRUCTION

SERVICES

Track removal 6.2 km
New track construction 6.8 km
Switch removal 30 pcs.
New switch construction 33 pcs.
Installation of fixed carriageway 32 m
Installation of top gravel 17,000 t
Tamping and grading
Tensioning and welding work: 800 welds
Overall coordination
Implementation planning
Surveying services

EQUIPMENT USED

Rail-road excavator
Track construction crane
Mechanical track and switch tamper
Locomotives

ASSIGNED STAFF

Average of 8 employees

IMPRESSIONS

TECHNICAL EQUIPMENT AND NOISE PROTECTION

SERVICES

Noise protection walls 2 km
Railway platform renovation
Cable routing systems 6 km
Signal foundation 80 pcs.
New construction of platform roof

EQUIPMENT USED

Rail-road excavator
Wheel loaders
Cable drum trailer

ASSIGNED STAFF

Average of 6 employees