    Project report

VDE 8.1 ABS Nürnberg-Ebensfeld, four-track expansion section Eltersdorf

PROJECT DESCRIPTION

The package contracted to LEONHARD WEISS GmbH & Co. KG in the scope of the traffic project Deutsche Einheit Nr. 8 [German unit no. 8] involves several construction divisions, thus giving it the status of a 'yellow construction site'.

The construction project is divided into 3 phases. The goal of the overall project is to reduce travel time by 50% to less than 4 hours on the Berlin-München route.

With the collaboration of various sections, even very elaborate and complex process can be carried out with speed and efficiency. This project is also another example of our motto - experience the joy of construction!

FACTS AND FIGURES

Customer: Deutsche Bahn AG, Nürnberg
Main construction period: 2013 – 2017
Section length: 4 km on the expansion section of Nürnberg-Ebensfeld, Erlangen construction section.
Expansion from 2- to 4-track section. Complex civil engineering and work during uninterrupted traffic. Complete implementation planning of the project.

ENGINEERING CONSTRUCTION

SERVICES

New construction of railway overpasses, Twofield construction technique. Pre-tensioned concrete box-section slabs or as frame structure (6 overpass structures)
Supporting walls in segments, height of up to 5.0 m

EQUIPMENT USED

Slewing cranes
Wheel loaders
Large-format drilling ring
Anchor drilling rig
Mini excavator

ASSIGNED STAFF

Average of 20 staff members

IMPRESSIONS

CIVIL ENGINEERING

SERVICES

Production of earth element (111,500 m3)
Production of earth wall (275,500 m3)
Production of frost and formation protection material (216,000 m3)
Soil improvement (19,500 m3)
Trenches/pits/retention basins (5,100 m)
Underground drainage (4,000 m) (incl. 180 shafts)
2 lifting systems
Settling/seepage and rainwater basins, surface area (2,500 m2)
Water retaining measures

EQUIPMENT USED

3-axle and 4-axle lorries Wheel loader
Excavators, rail-roader, mini excavator
Crawlers
Roller compactors
Cultivators and rock cutters

ASSIGNED STAFF

Average of 28 staff members

IMPRESSIONS

TRACK CONSTRUCTION

SERVICES

New track construction and superstructure for the planned 2nd and 3rd tracks
Track removal: 9,900 m
New track construction 16,500 m
Removal and/or renewal of switches: 2 units
New construction of switches and/or junctions: 14 units
Installation of ballast and fill ballast 57,000 t

EQUIPMENT USED

Kirow KRC 450 railway slewing crane
Kirow KRC 1200 railway slewing crane
Plasser 09/3X ballast tamper
Rail-roader
Robel SSP ballast plough

ASSIGNED STAFF

Average of 5 staff members

IMPRESSIONS

TECHNICAL EQUIPMENT AND NOISE PROTECTION

SERVICES

Planning, measuring services, overall coordination
Cable guidance system, including civil engineering for signalling equipment 9,000 m
Signal brackets, incl. foundation: 6 units
Platforms, incl. barrier-free access points: 2 units
Production of electrotechnical systems
Production of telecommunications, fire alarm and MAS90 systems
Catenary
Span poles: 157 units
Support masts: 233 units
Overhead line: 22,000 m
Sound insulating wall: 5,000 m

EQUIPMENT USED

Rail-roader
Cable reel trailer
Cable winch
Wheel loader
Mini excavator
Kirow 1200 railway crane
Sennebogen

ASSIGNED STAFF

Average of 12 staff members

IMPRESSIONS