    Project report

Highway construction – N1/N7 in Switzerland

PROJECT DESCRIPTION

The tender package contracted to LEONHARD
WEISS BAU AG will be provided by several construction
divisions, thus giving it the status of a 'yellow
construction site'.
LEONHARD WEISS will only be assisted by experienced
and capable sub-contractors in connection
with barriers, fencing work, markings and coating
work.

FACTS AND FIGURES

Customer: ASTRA-Bundesamt für Straßen, Filiale Winterthur
Main Construction period: March 2009 - November 2011
Operational release for traffic:November 2011
Maintenance of the N1/N7, 16 km N1 and 4 km N7

MAIN WORK FOR MAINTENANCE OF THE N1/N7, 16 KM N1 AND 4 KM N7.

Structural restoration of 34 highway structures
Expansion of a motorway bridge
Renewal of surfaces and bearing layers down to the subgrade, approximately 580,000 tonnes of removal and installation
Construction of a cable conduit approx. 290 km in length
Renewal and repair of drainage pipes 57 km; 470 new shafts and adaptation of 245 shafts
Renewal of barriers, markings and fencing

IMPRESSIONS

ROAD CONSTRUCTION

SERVICES

Renewal of surfaces and bearing layers down to the subgrade, approximately 580,000 tonnes of removal and installation.

Break-up of surfaces 340,000 tonnes
Removal of top soil and subsoil 25,000 cbm
Excavation / of gravel base course 160,000 cbm/108,000 cbm
Supply / move concrete kerb stones 30,000 m
Supply / install cold mix foundation 320,000 tonnes
Supply / install asphalt surface 260,000 tonnes
Supply / move fencing 33,000 m
Construction of barriers 25,000 m
Textured cold plastic marking 105,000 m
Marking film 13,000 m

 

ASSIGNED STAFF

An average of 10 crews (60 workers)

IMPRESSIONS

Projekt N1 / N7

 

Projekt N1 / N7

ENGINEERING CONSTRUCTION

SERVICES

Structural restoration of 34 highway structures and expansion of a motorway bridge.

Concrete construction 900 cbm
Site - concrete repair 11,000 qm
Concrete 1,550 cbm
Surface protection 5,000 qm
Epoxy resin sealing 10,500 qm
PBD sealing 13,000 qm
Melted asphalt 3,200 tonnes

 

ASSIGNED STAFF

An average of 20 workers

IMPRESSIONS

Projekt N1 / N7

 

Projekt N1 / N7

GENERAL CONTRACTOR NETWORK CONSTRUCTION

SERVICES

Renewal and repair of drainage pipes 57 km.

New drainage 30,000 m
Repair of drainage 27,000 m
New shafts 470 no.
Shaft repair 85 no.
Replacement track system over shaft including cover 160 no.
Supply / relocate cable protection conduits 290,000 m

 

ASSIGNED STAFF

An average of 7 crews (30 workers)