• headergrafik
    Aiming high for efficient
    and reliable quality
    Civil engineering / Constructual engineering

Renovation of the western supporting wall of the railroad embankment Lindau

Line 5362 km 151.927 – 152.485

Customer: DB Netz AG, Regionalbereich Süd
Construction period: 14 months Year of construction: 2020–2021
The original dam (approximately 540 m) was built from 1850 to 1855 for two tracks and extended on the eastern side around 1910. The western supporting wall was built as natural stone wall in 1855 and topsoiled with the existing material of the extension on the eastern side. Due to the bad state of the supporting wall and the construction of the boundary path which does not correspond to current standards any more the renovation needed to be carried out. The renovation was carried out from a work platform situated in the Bodensee by means of an anchored shell in sprayed concrete with attached casing as boundary path. The renovation of the western track will be carried out subsequently.
Concrete: 985 m³
Steel: 185 t
Sprayed concrete: 800 m²
Special underground engineering: 820 pcs. soil nails and micro piles 8,700 running metres
Track renovation: approx. 400 m

Frankfurt, PTS Fahrweg Nord

Customer: Fraport AG
Construction period: 28 months Year of construction: 2019–2021
Production of a total of 42 individual support and 21 horizontal member constructions. Production of the individual supports with hammer heads to the side as bearings for the track supports. The section North is produced in a high position of approximately 15 m to 20 m, so that the train can pass the terminals 1 and 2 without obstacles. The supporting heads protruded up to 7.5 m on the side, the free-spanning horizontal members are produced with aperture dimensions of up to 23.5 m. The bearing pedestals and upturns of the pedestals for the track supports are the limit of performance towards the system supplier of the elevated railway. Already in 2026, the new SkyLine Train is meant to connect the terminals 1 and 2 to the new terminal 3 on the southern side of the airport premises.



Particularities:

Construction step-by-step in existing facilities within the core area (freight handling) of the company Fraport AG during operation. Production of the individual structures as island construction sites. Monitoring of settling and vibration of existing buildings and urban railway tunnel during the entire construction phase. Drilled piles with a length of 28 m and an inclination of 5 degrees between existing buildings. Production of overlapping bored pile walls as remaining supporting structures for the future operation of the elevated railway.

16,000 m³ concrete
4,700 t armouring steel
398 pcs. bored piles D=1.20 m length: 10–28 m
210 pcs. prefabricated parts in reinforced concrete

S21, PFA 1.6a, Interregiokurve Ingenieurbauwerke

Customer: DB Projekt Stuttgart – Ulm GmbH
Construction period: 21 months Year of construction: 2019–2020
The joint venture ARGE INGBAU Interregiokurve S21, composed of the joint venture partners LEONHARD WEISS and BAUER Spezialtiefbau GmbH, realised the level crossing of the line 4721 over the access routes to the carriage siding Untertürkheim, as well as the routing to the newly constructed freight train return loops in Untertürkheim. The following buildings needed to be produced:

Ramp construction consisting of a cantilever retaining wall (50 m), through structure (160 m) and framework structure (320 m)
Flying junction over 2 tracks (total length: approx. 89 m)
Overlapping bored pile wall anchored backwards (length approx. 61 m)
Several auxiliary buildings (overlapping bored pile wall, Berlin-type support system with and without anchoring construction)

Furthermore, execution planning was also carried out by LEONHARD WEISS. The construction works in the area of the tracks were carried out during shutdowns. These were works next to operational tracks of DB and in the protected area around medical springs.

QUANTITY

Flying junction:

Armoured concrete: 3,477.4 m³
Steel: 636.8 t

Ramp construction and cantilever retaining wall:

Armoured concrete: 10,476 m³
Steel: 1,704.3 t

Stuttgart-Ulm, PFA 2.1 c, Lot 4, section Weilheim/Teck

Customer: DB Projekt Stuttgart-Ulm GmbH
Construction period: 67 months Year of construction: 2015–2020
In connection with the largescale project Stuttgart 21 the new construction of an approx. 4.5 km long section of the high-speed line Wendlingen-Ulm was carried out. Preparation of execution planning and construction of all engineering and earth buildings incl. drainpipes and noise protection measures, as well as extensive flood protection measures.

Numbers, dates, facts of the individual buildings:

Railway overcrossing Lindach:

3 field railway overbridge in pre-tensioned concrete construction
Spans 18.50 – 23.50 – 18.50 m, Total length 60.50 m, Overall height approx. 1.25 m, 205 m in-situ concrete piles 90 cm, 1,415 m³ concrete sub-construction, 600 m³ concrete superstructure, 320 t armouring steel, 39 t prestressing steel

Railway L 1200:

2-field railway overbridge in pre-tensioned concrete construction, with monolith pier connection
Spans 24.75 + 24.75, Total length (between end bearings) 49.50 m, Length of superstructure 51.00 m, Overall height (superstructure) 1.30 m

Flood retention basin Seebach – retaining wall:

Flood retention basin with a retention volume of approx. 90,000 m³ including all water engineering structures.
1,650 m² overlapping bored pile wall, 1,450 m bored piles Ø120, 5,300 m³ concrete, 640 t armouring steel, 8.00 – 10.90 m height

Road crossing Holzmadener Straße:

2-field road crossing
Spans 21.00 + 14.00, Total length (between end bearings) 35.00 m, Length of superstructure 36.60 m, Overall height 0.90 m

Tunnel "Rastplatz vor dem Aichelberg" (motorway layby):

Framework construction in open construction method
12,500 m² formwork, 12,900 m³ concrete, 2,510 t armouring steel, 253 m length, 12.30 m inner width between the tunnel walls, 28 blocks

Basement waterproofing:

Through construction with floor slabs up to 2.50 m
4,100 m² formwork, 6,900 m² concrete, 1,100 t armouring steel, 222 m length, 12.30 m inner width between the through walls, 23 blocks

Modernisation train station Wangen im Allgäu

Customer: DB Station & Service AG, Regionalbereich Südwest
Construction period: 11 months Year of construction: 2019
Accessible conversion of the train station in Wangen im Allgäu. Production of a pedestrian underpass with stairways and elevators. New interior and outdoor platforms, as well as bike parks and access ways to the station premises.

PARTICULARITIES

6-week shut down (only logistics runs). The stretch was electrified at the same time. Special proposal by LEONHARD WEISS, instead of a delay the pedestrian underpass was constructed in open construction method in a very short period of time. Exactly fitting formwork elements were used to speed up the works.

QUANTITY

210 m² bulkhead system
530 m³ concrete
90 t steel
270 m sealings

Renovation of fly-over, Nuremberg

Customer: Deutsche Bahn AG
Construction period: 7 months Year of construction: 2016–2017
Replacement structure for a fly-over of Deutsche Bahn. The line on top consists of 2 tracks, the line below of 1 track. Production of the entire structure in lying position, approximately 67 m away and about 2.13 m superelevated. The weight of the structure amounts to about 3,200 t. Dismantling of railway embankment incl. tracks and demolition of the old structure during shut down, preparation of subsoil, installation of the structure, backfilling and production of the superstructure and the tracks.

PARTICULARITIES

Extremely narrow construction space, not much storage space, difficult access, production in superelevated position lying on the side, shut down during eight days for dismantling, installation and reconstruction of the entire facility until the first train run.

QUANTITY

1,500 m³ concrete
300 t steel (incl. prefabricated parts)
103 prefabricated slabs with a total weight of approx. 730 t
8,500 m³ excavated earth
1,000 m³ demolished concrete
7,000 m³ backfilling

STRUCTURE:

8 m high
12 m wide
35 m long
67 m distance to construction site
2.13 m de-piling height

ABS Hanau-Nantenbach bypass Schwarzkopftunnel

Customer: DB Netz AG, Frankfurt
Construction period: June 2013–November 2015 Year of construction: 2013–2015
New construction of a bypass between Heigenbrücken and Laufach in connection with the upgrade of the railway line Hanau-Nantenbach. A total of 470 m supporting walls, between 4-11 m of height, 300 m pile head beams, 1,270 m through structures with walls up to a height of 13 m, 1,530 m tunnel in open building method, 2 railway and farm road crossings, two passages, as well as one stop station and the equipment of the entire bypass line were carried out. For these buildings a total of 120,000 m³ concrete and 20,000 t steel were used.

B 535, Schwetzingen-Plankstadt Tunnel

Demanding tunnel construction

Customer: Karlsruhe regional council, official headquarters in Heidelberg, Heidelberg-Wieblingen
Construction period: 18 months Year of construction: 2008–2009
As part of the road development for the B535 Schwetzingen-Plankstadt bypass, running the road in a tunnel near the overlying surface proved necessary.

The tunnel has two tubes: the "northern tube" with a length of 650 m and the "southern tube" with a length of 450 m. The internal width is 9.50 m per tube; the section lengths of tunnel blocks are generally 10 m
180 m concrete retaining walls in the connection to the tunnel
Operations building
Storm water detention tank with sedimentation plant
Backfill and overfill of the tunnel
Noise protection before and after the tunnel
Noise protection walls along the already constructed new L 543
Drainage facilities and complete road construction inside and outside the tunnel
Concrete 40,000 m3 (about 600 m3 per block)
Reinforcing steel 3,800 t