    Quality and safety in construction
    is priority at LEONHARD WEISS
    General contractor network construction

VDE (German Unity Transport Project) 8.1 BA 2400 Zapfendorf – Laying of cables

Rapid data transfer also during Construction period

Customer: DB Netz AG, Erfurt
Construction period: 22 months Year of construction: November 2015–August 2017
New laying of all telecommunication cables, fibre optic cables, as well as copper cables incl. all planning services. The cable along the line, which was provisionally laid into the building plot, had to be continuously adapted during the construction progress together with its provisional cable conduit.
20 km copper cable and 45 km fibre optic cable were processed.

IKI Koblenz-Cochem

Mobile communication at the Franco-German border

Customer: DB Netz AG, Frankfurt am Main
Construction period: 8 months Year of construction: 2015–2016
Due to the narrow conditions (river Mosel, support wall, vineyards) the works could only be carried out during short shutdowns overnight and over the week-end, as well as during road and track shutdowns.
Cable ducts and cable ducts made of glass fibre reinforced plastic were laid, pipes were installed in platforms, road and track crossings, road crossings were constructed, 53 km fibre optic cable laid, steel pipe crossings in the area of the track were constructed, cable jointing manholes were installed in the area of the track.

TANV II Backnang - Waiblingen

Mobile communication in the Rems-Murr region

Customer: DB Kommunikationstechnik, Ludwigsburg
Construction period: 7 months Year of construction: 2015
10 km new route construction, 7 km existing roads, 40 km fiber optic cable. Restricted invitation to tender because of 100% private DB AG resources and implementation during regular railway operations of concentrated urban railway traffic

IKI West 3 Troisdorf - Betzdorf

Fiber-optic technology for the company's internal network

Customer: DB Netz AG
Construction period: 16 months Year of construction: 2014–2015
Approximately 19 km of concrete cable channel, new construction in short shutdown periods or during regular railway operations. Installation of approx. 60 km fiber-optic cables including assembly services. Work independent from track activity only partially possible. Multiple cable installation on bridges and in tunnels due to topographical conditions.

GSM-R Sigmaringen - Aulendorf

Three stations in harmony

Customer: DB Netz AG, Freiburg
Construction period: 4 months Year of construction: 2010
Underground cable laying, cable laying, road and rail track crossings, concrete duct. Equipping of 3 train stations with fiber optic cable technology.

GSM-R Offenburg - Hausach

Fiber optic technology at the gateway to the Black Forest

Customer: DB Netz AG, Freiburg
Construction period: 6 months Year of construction: 2010
Underground cable laying, cable laying, road and rail track crossings, concrete duct, equipping of 3 train stations with fiber optic cable technology. Extremely ingrown existing cable routes, existing cable routes requiring renovation, heavily used DB main line.