    Quality and safety in construction
    is priority at LEONHARD WEISS
    General contractor network construction

S21 equipment Stuttgart Untertürkheim

We switch on the light for Stuttgart 21

Customer: DB Projekt Stuttgart – Ulm GmbH
Construction period: 48 months Year of Construction: 2021–2025
New construction of approx. 16 km of concrete cable duct
Laying out of approx. 3 km temporary cable duct routes
Production of 90 track crossings in open building method
Approx. 500 km redundant laying of cables (control, communication, and safety system, telecommunication, medium voltage, 50 Hz)
New construction of 4 signal brackets (3 foundations with anchored driven casing pipes and one foundation by means of bored pile DN 1,200 mm)
Dismantling of one signal bracket and conversion of one signal bracket
Production of 4 foundations for buildings for control and switch facilities, 3 ground slabs were realised by means of Duktil bored pile foundations and one foundation by means of foundations in prefabricated parts.

S21 Bad Cannstatt

For the German digital railway

Customer: DB Projekt Stuttgart – Ulm GmbH
Construction period: 50 months Year of Construction: 2021–2025
Yellow construction site with Gleisbau Göppingen (Track Construction Göppingen)
Execution of underground cable works requiring 80 cable crossings, 15,000 m of cable duct and 76 signal foundations
Foundation of 16 signal brackets by means of drilled piles with a diameter of 88 cm and up to 22 m of length with railway foundation construction train, which received a special permit for this construction project

Particularity:

speeding up of the project by the customer: a total of 11 weeks shutdown from May to July 2023.
Assignment of up to 50 workers and 5 road-rail excavators around the clock.

Breisgau suburban railway 2020, Höllentalbahn Ost – flyover Bachheim

Elevators accessible for the handicapped for the station Titisee

Customer: DB Engineering & Consulting, Karlsruhe
Construction period: 2 months Year of construction: 2019
We were awarded the contract for the execution planning of the foundation of the road flyover at km 56,500 and the production of 600 running metres of large bore piles DN 880 according to DIN EN 1536. Separate test piles and pile tests were conducted to prove the vertical load bearing capacity.

Breisgau suburban railway 2020, Höllentalbahn West – station Hinterzarten

Elevators accessible for the handicapped for the station Hinterzarten

Customer:Joint venture Zürcher, Vogel, Joos
Construction period: 2 months Year of construction: 2018
Two building pits for handicapped accessible elevators. Limited height, building pits in ground water
Detailed planning
600 running metres bored piles DN 300
30 m³ underpinning with sprayed concrete
Steel reinforcement, excavation, water drainage

Breisgau suburban railway 2020, Höllentalbahn West – station Titisee

Elevators accessible for the handicapped for the station Titisee

Customer: Joint venture Zürcher, Vogel, Joos
Construction period: 2 months Year of construction: 2018
Two building pits for handicapped accessible elevators, limited height
Detailed planning
370 running metres bored piles DN 300
15 m² underpinning with sprayed concrete
Steel reinforcement, excavation