Home
Contact
Languages
Deutsch
English
LEONHARD WEISS-Group
Toggle navigation
Company
about us
Management
Locations
Philosophy
Company history
Awards
Portfolio
our expertise
Overview of our expertise
Structure upgrade and mastic asphalt
General contractor overhead line construction
Project management infrastructure projects
General contractor network construction
Track construction
Track construction machines
Civil engineering / Constructual engineering
Network construction
Resources
Turnkey construction
Road and civil engineering
Subsidiaries
Modern building
Tools / Methods
BIM - Building Information Modeling
BIM – Bauen in anderen Dimensionen
BIM Coordination
Collision control / Clash detection
Model based quotation processing / Tender offers
Visualisation / Rendering
BIM Planning
Stocktaking
Task management
Building documentation
Operation / Facility Management
LEAN-Construction
Career
your future
RESPONSIBILITY
live values
Sustainability
Quality
Compliance
Environmental protection
Occupational health and safety
Social responsibility
Media / Press
downloads
Images
Video
Documents
Extend service life,
save costs
Structure upgrade and mastic asphalt
Home
Structure upgrade and mastic asphalt
Tunnel renovation and equipment
Our service spectrum
Toggle Dropdown
Repair/traffic infrastructure
Renovation of park structures
Sealing and mastic asphalt
Poured asphalt for roads
Poured asphalt for buildings
Tunnel renovation and equipment
Innovative bridge systems
Lifting up and relocation of buildings
Overhauling of tunnel Neckartalfingen B 297
Customer:
Regional Council Stuttgart, Office Göppingen
Construction period:
6 months
Year of construction:
2016–2017
Total length 1600 m
Surface sealing and melted asphalt approx. 10,000 m2
Surface concrete overhaul approx. 7,600 m2
Renovation of concrete back bars 1,580 m
Renovation of sealing and asphalt layer, as well as overhauling of tunnel walls and trough walls
A 81 Schönbuchtunnel
Customer:
Regierungspräsidium Stuttgart (Stuttgart Regional Council
Construction period:
25 months
Year of construction:
2014–2016
Renewal of 600 m3 curbs
10,000 m2 of surface protection C coating
35,000 m2 of asphalt work
1,000 m2 of high-pressure water jet removal, renewal with shotcrete, depth 5 – 10 cm
Renewal of connection tunnel and fire protection doors
L 5036 Branichtunnel, Schriesheim
Customer:
Regierungspräsidium Karlsruhe (Karlsruhe Regional Council)
Construction period:
3 months
Year of construction:
2015
12,000 m2 of surface protection C coating
350 units of block numbers
B 28 Tunnel, Blaubeuren
Customer:
Regierungspräsidium Tübingen (Tübingen Regional Council)
Construction period:
8 months
Year of construction:
2012
7,800 m2 of tunnel cleaning with subsequent renovation of damaged areas
75 m3 of high-pressure water jet removal, re-profiling with sprayable polymer-modified cement concrete mortar
320 m3 of demolition and reconstruction of curbs
28 cable ducts
1,200 m2 of surface protection 8 and 400 m2 of surface protection C coating
2,200 m2 of alucubond facade removed and replaced
6,000 m2 of surfacing work
A 8 autobahn Lämmerbuckeltunnel
Customer:
Regierungspräsidium Stuttgart (Stuttgart Regional Council)
Construction period:
4 months
Year of construction:
2011
Removal of 7,000 m2 of wall tiles and underground preparation with high-pressure water jet
1,050 t of shotcrete, 1,850 composite anchors
7,500 m2 of fine filler, 5,000 m2 of surface protection C coating
500 m2 of damaged areas down to 15 cm deep
B 27 tunnel, Dusslingen
Customer:
Regierungspräsidium Tübingen (Tübingen Regional Council)
500 m of surface protection C tunnel coating (approximately 5,600 m2)
2,000 of hydrophobic cover treatment
190 block numbers
Sealing of 4,000 m2 of tendon and tunnel ceiling