Dump site Einöd, backfilling phase II, 4th construction phase, base sealing

Customer: Landeshauptstadt Stuttgart, AWS Abfallwirtschaft Stuttgart
Construction period: 8 months Year of construction: 2022–2023
Expansion of the existing base sealing on a total surface of approx. 11,000 m²
Delivery and installation of approx. 14,000 m³ mineral sealing material according to the national quality standard and dump site requirements
Delivery and installation of approx. 7,000 m² plastic sealing sheeting incl. connections to the already existing base sealing
Delivery and installation of approx. 7,000 m² sand blanket on the newly installed plastic sealing sheeting incl. connections to the already existing base sealing
Delivery and installation of approx. 17,000 m² woven filter medium and separation textile on mineral sealing and drainage layer
Delivery and installation of approx. 3,500 m³ drainage layer
Installation of approx. 12,000 m³ stabilisation of embankment with material already available at the site of the customer
Delivery and installation of approx. 130 m deep drain (diameter 315 and diameter 400)

Recultivation of dump Blinksteige construction phase 3

Surface sealing of the former garbage dump “Am Blinkbach“

Customer: City of Rothenburg ob der Tauber
Construction period: 6 months Year of construction: 2022
Surface sealing of a former garbage dump on a surface of about 18,500 m²
Delivery, installation, and processing of about 5,000 m³ sealing material according to the requirements for dumps
Installation of about 18,500 m² of a geosynthetic drainage mat
Installation of about 35,000 m³ recultivation material on the drainage mat
Subsequent installation of topsoil on 18,500 m²
New construction of 250 seepage water drainpipe

Renovation basic sealing of the dump Reutehau

Customer: Gesellschaft im Ostalbkreis für Abfallwirtschaft
Construction period: 7 months Year of construction: 2022

The landfill body needed to be renovated in certain areas due the landslides and water outlets below the basic sealing during the year 2002.

Dismantling of the basic sealing composed of

about 1,000 m³ mineral drainage layer
about 130 m seepage water drainpipe (opening of the undamaged/active dump drainage)
about 3,000 m² protective mat and sealing sheeting
about 5,000 m² soaking and softened mineral sealing layer

New construction substratum basic sealing

Installation of a 40 cm thick seepage layer (about 2,200 t) and seepage water drainpipe under the basic sealing
Execution of an 80 m wash-boring under the basic sealing and the landfill body

New production of a basic sealing

Installation of a new geologic barrier
Installation of a new and processed mineral sealing layer (2,250 m³)
Installation of a new plastic sealing sheeting and protective mat on about 3,000 m²
Installation of the old and processed drainage layer on the protective mat
Installation of about 130 m new seepage water drainpipe on new pipe bedding (dump mixture M9)

Dumpsite Eberstadt – installation base sealing construction phase II

Customer: Landratsamt Heilbronn Abfallwirtschaftsbetrieb
Construction period: 7 months Year of construction: 2020
3,600 m² profiling
2,700 m³ delivery and installation of mineral sealing
3,200 m² geotextile protective membrane, as well as separation and filter membrane with BAM-approval
100 m² base sealing (Münchner Mischung M9)
350 m PEHD pipeline construction DA315

Dump site Einöd – DK II, bottom sealing 3rd construction phase

Expansion of the existing bottom sealing in the area of the embankment

Customer: Regional Capital Stuttgart
Construction period: 6 months Year of construction: 2017
6,000 m² fine formation for plastic sealing sheet
3,500 m³ mineral drainage layer
6,000 m² geo-textile protective membrane, as well as separation membrane and woven filter medium
6,000 m² plastic sealing sheet PE-HD (2.5 mm) with BAM certification
6,000 m² sand screen mat (mineral dump sealing sheet)
3,500 m³ support shell (soil material) (1.5 – 3.0 m)
160 m PEHD pipe line construction

New construction of slag storage at the Vogelsang landfill, Heilbronn

Asphalt installation during night shifts for compliance with the required short construction period

Customer: The city of Heilbronn, Disposal operations
Construction period: 3 months Year of construction: 2015
23,000 m3 of earth-moving
16,500 m2 installation of 14 cm asphalt base and 4 cm asphalt surface
16,500 m2 60 cm thick gravel base layer installation
Construction of a retention basin with a surface of 1,350 m2, including asphalt waterproofing
Placement of a waste collecting cell with flow-dividing structure and reservoirs
Construction of protective degassing with horizontal gas drainage and gas pipe stub-outs under the asphalt surface
Construction of utility lines (electricity, water, conduits)

 

 

Hasenbühl landfill, Schwäbisch Hall-Hessental

Permanent surface sealing

Customer: Schwäbisch Hall District Office
Construction period: 26 months Year of construction: 2015–2017
Executed as a joint venture
Section-by-section demolition of temporary waterproofing
Re-profiling of the landfill area
Application of a new permanent impermeable plastic liner
Laying of bentonite mats and protective membranes
Construction of a 30 cm thick drainage layer to drain the surface water
Installation of a 2 m thick layer of reclamation soil for planting and / or for technical installations such as photo-voltaic panels (total amount of reclamation soil approximately 200,000 t)
Installation of approximately 100,000 t substitute landfill construction materials
Implementation of additional measures for drainage and gas release of the landfill

Landfill, Sinsheim

Closure of the 1st landfill cell

Customer: AVR Abfallverwertungsgesellschaft des Rhein-Neckar-Kreises mbH
Construction period: 6 months Year of construction: 2009
Expansion of the existing sorting system with a container storage space and a bale loader for recyclables. Construction of surface sealing as a TASI control system over landfill cell I for landfill class II.
Road widening with landfill asphalt
Work on the existing gas system
In-situ concrete floor plate: 2,600 m2
Asphalt base course and asphalt concrete (acid-resistant): 1,400 m2
Earthwork: 15,000 m3
Profiling materials: 30,000 m3
Mineral seal: 15,000 m3
Impermeable plastic liner and protective membrane: 30,000 m2
Gravel: 17,000 t
Woven filter: 30,000 m2
Reclamation soil: 30,000 m3
Landfill asphalt: 1,500 m2