    Project report

VDE 8.1 ABS Nuremberg - Ebensfeld, PA 21 Altendorf - Strullendorf

PROJECT DESCRIPTION

The upgrade of the high-speed line VDE 8.1 between Munich and Berlin is one of the largest construction projects in Germany. LEONHARD WEISS has already contributed to this project with several PMInfra construction sites over the past years.

For the project PA 21 Altendorf-Strullendorf we carry out the project management infrastructure projects (PMInfra) with the business divisions track construction, civil engineering, engineering construction and the railway technology division (general contractor network construction) for a 10 km long section of the leg Nuremberg-Ebensfeld including the creation of the execution planning for all trades, during which the two-track, electrified existing line is upgraded to tour tracks.

This includes all earthworks, drainage of the line, underground cable engineering, noise protection walls, track construction, platform works, superstructure works, as well as engineering construction.

NUMBERS, DATES, FACTS

Customer: DB Netz AG, Nuremberg
Construction period: April 2021 to December 2025
Length of the project section 10 km
Upgrade of the track system from two to four tracks
New construction of 44 km of tracks and 12 points
New construction of 11 railway/road flyovers and four passages
Underground engineering, drainage, and underground cable engineering on the entire section
Conversion of 3 stopping points
Erection of 11,000 m of noise protection walls
Construction of 44 km catenary system
Execution planning for the trades underground engineering and drainage, engineering construction, noise protection walls, track superstructure/underground cable engineering, electric power systems 50Hz, control, communication, and safety system PT1 IECC and computer-controlled relay interlocking, telecommunication facilities, catenary.

ASSIGNED PERSONNEL (FOR ALL TRADES)

70 -150 industrial workers
25 technical/commercial employees 
 

ENGINEERING CONSTRUCTION

PERFORMANCES

New construction of 3 passages (km 46.7, km 47.3, km 50.7)
New construction railway flyover Lindlesgraben
New construction road flyover Lindlesgraben
New construction railway flyover Maximilianstraße
New construction pedestrian underpass Hirschaid
New construction railway/road flyover Friesnitzgraben
New construction road underpass Möstenbach
New construction railway flyover Auweg
New construction pedestrian underpass Bahnhofstraße in Strullendorf
New construction railway flyover Zeegenbach
New construction supporting wall km 55,1
New construction road flyover B505 – Zweifeldbrücke
New construction passage Stadtwald during shutdown
New construction of 10 pump stations
 
 

 

EQUIPMENT USED

Various construction cranes
Concrete pumps
Rotary drilling facilities and vibratory equipment

ASSIGNED PERSONNEL

20 industrial workers
5 technical employees

IMPRESSIONS

UNDERGROUND ENGINEERING

PERFORMANCES

New construction deep drains 10,500 m (DN 250)
New construction drainage pipelines 9,000 m (DN 200 – DN 800)
New construction plastic and concrete manholes incl. drop manholes 450 pcs. (DN 800 – DN 2000)
New construction pressure pipes 3,500 m (DN150 – DN 400)
Production of through-press pipes partly in ground water
Infiltration ditches 1,200 m
Depressions / trenches 8,000 m
Production of ramming and boring platforms, construction pits, as well as backfilling for 13 road or railway flyovers
Construction-temporal water retaining measures at the structures
Earthworks 60,000 m³ removal
Removal of track ballast 60,000 m³
Production formation layer 250,000 m²
HProduction protection and base layers (frost protection layer/formation protection layer) 200,000 m³
Production of escape and emergency routes
Production of agricultural roads parallel to the tracks 7 km
Production of construction roads 8 km
Production of 1 infiltration, 2 rainwater retention and 2 rainwater purification basins
Demolition of passages 5 pcs.
Demolition of railway flyovers 6 pcs.
Demolition of road flyovers 2 pcs.
Demolition of pedestrian underpasses 2 pcs.
Demolition of 4 residential houses, as well as 12 auxiliary buildings/halls/garages
Reuse / disposal of soil and demolition material
Safeguarding of various existing supply lines of third parties

OTHER

Construction site clearing
Forest clearance
Measures in connection with landscape conservation requirements
Erection of safety fences 2.5 km
23 building site equipment areas along the route
Support of archaeological examinations
Warfare material examination
Execution planning
Traffic safety partially with complete shutdown/deviation
Production of structures along the tracks 5 km
Deinstallation of ground water measuring points

EQUIPMENT USED

PBulldozers
Chain dredgers, long excavators, mobile excavators, and skid loaders
Large and small wheel loaders
Roller compacters
Graders
Asphalt finishers and rollers
Soil stabilisation – large milling and gritting vehicles
High pressure road sweepers
Trucks, trailer trucks and four-axle vehicles, silo trucks
Tractors
Water drums
Crusher plant

ASSIGNED PERSONNEL

30 industrial workers
8 technical employees

IMPRESSIONS

TRACK INFRASTRUCTURE CONSTRUCTION (TRACK CONSTRUCTION / GENERAL CONTRACTOR NETWORK CONSTRUCTION)

PERFORMANCES

TRACK CONSTRUCTION

Four-track upgrade on a stretch of 10 km in connection with various construction levels in progress
Installation and deinstallation of 3 construction temporary points
Installation and deinstallation of 9 points (type 1200)
New construction of 44 km of track incl. ballast bed / dismantling of 24 km of track
Installation of sub ballast mats at the artificial structures

PLATFORM CONSTRUCTION

New construction of 3 middle platforms incl. equipment and accesses
Production of structures along the track for production on one side
New construction of 2 side-boarding platforms incl. equipment and accesses
AConstruction, provision and dismantling of 5 temporary platforms

CONSTRUCTION OF NOISE PROTECTION WALLS

New construction of 10.9 km of noise protection walls (2.223 foundations)
New construction of 520 m of sheet pile walls incl. headboards






UNDERGROUND CABLE ENGINEERING

New construction of approx. 11.5 km cable conduit system incl. cable crossings in open and closed construction method

CATENARY LINE CONSTRUCTION

New construction of 44 km of catenary system (575 foundations for catenary system) Plus integrated masts for catenary system in the noise protection wall
New construction of local control system

TECHNICAL EQUIPMENT

New construction of 18 signal brackets (drilled pile foundations)
New construction of 2 point heating stations
Electric power systems connection of the stopping points Buttenheim, Hirschaid, and Strullendorf
Electric power systems connection of 10 pump stations
Telecommunication equipment of the stopping points Buttenheim, Hirschaid, and Strullendorf
Support in the realisation of temporary construction levels for telecommunication and control, communication, and safety system site clearing
VRelocation of 3 concrete switch cabinets

OTHER

Building area inspections in the entire section of the line
Implementation of the emergency access concept
Lighting facilities
Control, communication, and safety system auxiliary point equipment

EQUIPMENT USED

Road-rail excavators, wheeled excavators, chain dredgers and skid loaders
Road-rail boom lifts / work platforms / road-rail aerial platforms
Road-rail ramming device
Track construction technology (lifting apparatus and straightening equipment / sleeper laying equipment / etc.)
Large and small wheel loaders
Transport services (trucks and tractors)
Graders / bulldozers / crawler loader
Roller compacter
Unloading unit for long rails
Track and point tamping machine / ballast grader
Locomotives / work trains
Railway rotary crane
Truck-mounted crane
Ramming and drilling equipment
Small equipment technology
Cable draw-in technology

ASSIGNED PERSONNEL

20 industrial workers
120 industrial workers during peak times incl. subcontractors
6 technical employees