    Track construction

Platforms and railway crossings

Railway stations and platforms are the point of access to the railway network. Travelers can change from the train to the car, bus, tram or bicycle. LEONHARD WEISS offers you the following services:

Renewal, alteration and extensions of platforms in standard or modular designs (production parts) including all access paths and platform equipment
Creation of platform accesses without barriers
Pedestrian underpasses and overpasses
Creation of Park & Ride facilities
Creation of complete station forecourts

We provide services related to all aspects of urban transport infrastructure.

 

Station modernisation program Beimerstetten

Customer: DB Station & Service AG
Contsruction period: 10 months Year of Construction: 2021
Dismantling buffer stop track
2 x 450 m realignment of track incl. enlarging of embankment
2 pcs. auxiliary bridges
New construction pedestrian undercrossing incl. encasement of stairways and installation of a lifting station incl. complete equipment
New construction middle platform and platform along the station building
New construction station forecourt
New construction low track passage lighting
Underground cabling works, laying of cables, signal foundations, 50 Hz services
Production of 600 m deep drains
Adaptation of noise protection wall

Höllentalbahn Ost

Customer: Deutsche Bahn AG / General Contractor
Network Construction LEONHARD WEISS

Contsruction period: 17 months Year of Construction: 2018–2019
3 pcs. level crossings
10 pcs. passages
2 pcs. flyovers
7 pcs. traffic stations
5 pcs. lowering of tunnels
4 pcs. emergency and assembly points
12 km road
40 km control, communication, and safety system and telecommunication technology

Renovation level crossing Talhausen

Customer: DB Netz AG, Karlsruhe
Construction period: 2 months Year of construction: 2021
Conversion of the signals of the level crossing with widening of the road Underground cable engineering on the line and laying of cables
8 x driven casing foundation TECDOWN
640 m² conversion of road surface
4,500 m control, communication, and safety system cable
Cable civil engineering for level crossing
Strail track covering

Level crossing Aulendorf – Bad Waldsee

Customer: DB Netz AG, Karlsruhe
Construction period: 8 months Year of construction: 2021–2022
Six level crossings, underground cable engineering, laying of cables, signal foundations, road adaptation works, 50Hz performances.
50 invatec TECDOWN driven casing foundations
13,000 m control, communication, and safety system cables
30 cable chutes
3,500 m invatec glass-fibre reinforced plastic cable duct, size 1a
Foundations of concrete control stations

Superstructure renovation & accessible upgrade train station Zaisenhausen

Customer: Albtal-Verkehrs-Gesellschaft mbH
Construction period: 10 weeks, including 6 weeks complete shutdown
Year of construction:
2021

dismantling and accessible new construction of 2 platforms with 120 m each, incl. new cable routes and cable crossings
track renovation incl. uplifting of gradient
soil improvement with lime-cement mixture of both train station tracks with 870 m each
production of 500 m deep drains and 350 m trenches
new construction of 410 m cable duct and 600 m boundary path
6.5 km maintenance tamping

Superstructure renovation & accessible upgrade train station Bauerbach

Customer: Albtal-Verkehrs-Gesellschaft mbH
Construction period: 4 months, including 6 weeks complete shutdown Year of construction: 2021
dismantling and accessible new construction of 2 platforms with 120 m each, incl. new cable routes and cable crossings
track renovation incl. uplift of gradient 1800 m open line
track renovation of both train station tracks with 900 m each
soil improvement with lime-cement mixture of both train station tracks with 900 m each
production of 500 m deep drains and trenches
new construction of 500 m cable duct and 1000 m boundary path
maintenance tamping

Modernisation train station Wangen

Customer: DB Station & Service AG
Construction period: 10 months Year of construction: 2019
550 m dismantling interior and centre platform
340 m new construction of interior platform and outdoor platform
4,500 m ductwork for cables
39 cable assembly chutes
6,500 m laying / drawing-in of cables
2,500 m² pavement works
Complete renovation of point heating facility incl. supply
New construction of supply and distribution of electric facilities
4,000 m² removal of soil
10,000 t dump materials
11,000 t disposal (soil, asphalt, demolished concrete, old ballast)
210 m² bulkhead system
530 m³ installation of in-situ concrete
90 t reinforcement steel
270 m² sealing of buildings
Installation of a pumping systems incl. complete equipment
New construction of 2 staircases and bike parks