S&C renewals

Switches and crossing are the critical points in any railway network where tracks separate, cross each other and reconnect. Ever increasing speeds and wheel loads continue to place additional stress on these vital components of railway infrastructure. As such they demand constant attention and intensive maintenance.

LEONHARD WEISS is your specialist for renewal, maintenance and repair of switches ranging from simple industrial yard switches to complex high-speed switches. We excel in all track types, whether ballasted or slab based. Our modern high-performance cranes enable us to install large prefabricated switch parts of the highest quality without affecting normal railway traffic.

Plochingen renovation of points

Customer: DB Netz AG
Construction period: 2 months during 3 shutdowns for conversion
Year of construction:
2023

Dismantling of 20 points
Installation of 19 points
Pre-assembly of 17 points and installation by means of track construction crane
2 pcs. installation in a pit
Closing of gap
Removal of 3,500 t excavated ballast on LEONHARD-WEISS dump truck incl. handling of material
Installation of 2,800 t track ballast from railway wagons
Underground cable works incl. relocation of 5 signals

Particularities:

Difficult work due to limited working space and the hot spell in July 2023

VB 22 Waiblingen

Customer: Deutsche Bahn AG
Construction period: 4 months Year of construction: 2022
6 pcs. renovation of points with complete renovation of track bed
including: 2 pcs. 54-500 1:12 / 1 pcs. 54-1200 1:18.5 / 1 pcs. 54-760 1:14 / 2 pcs. 49-190 1:9
3 pcs. renovation of buffer stop
1 pc. closing of gap in a curve to the right 49-190 1:7.5
Track renovation traditional method: 760 m
Track renovation by means of machines: 520 m
Complete renovation of track bed: 760 m
Ballast cleaning: 520 m

VB22 Stuttgart-Untertürkheim

Customer: Deutsche Bahn AG
Construction period: 3 months Year of construction: 2022
1 pc. track renovation with complete renovation of track bed
Contrary flexure turnout (ABW) 54-190-1:9 l(B)
New construction of deep drain 630.4 m
Complete renovation of track bed (backfilling / base ballast) with ballast cleaning machine (VBE): 899.4 m
Track renovation by means of machines: 899.4 m
Complete renovation of track bed traditional method (VBE) with excavator: 1,922.5 m
Track renovation traditional method: 1,922.5 m
Installation of rails 2 pcs. (Se2): 191.7 m
Installation of formation protection layer traditional method (KG1 / KG2): 978.4 m
Flushing of deep drain: 1,552.1 m

VB22 Stuttgart Hafen-S-Ost

Customer: DB Netz
Construction period: 4 months Year of construction: 2022
3,334 m track renovation (traditional)
2,784 m complete renovation of track bed (traditional)
550 m ballast cleaning by means of machines (in continuous process)
2,509 m production of side path
Point renovation with complete track bed renovation
1 x simple point 49-190-1:9 l(B)
1 x simple point 49-300-1:9 l(B)

Trapeze of points Hirschgarten

Customer: DB Netz AG, Munich, 2nd home linee
Construction period: 19 months Year of construction: 2021–2023
Dismantling of 460 m track
Removal of old ballast 1,000 t
Removal of 850 t soil
Installation of formation protection layer 800 t
Installation of new ballast 1,600 t
Installation of 2 points ABW 60-300-1:14 l B (WITEC) (VS)
Installation of 2 points IBW 60-300-1:9 r B (WITEC) (VS)
Installation of point heating for 4 points
Installation and dismantling shutdown type I for 4 points
Foundation, production, and installation of signal brackets

Aalen main station

Customer: Deutsche Bahn AG, Stuttgart
Construction period: 8 months Year of construction: 2021–2022
- Difficult conditions due to heavily delayed material supplies because of supply shortages
- Award of transport works to LW due to supply difficulties of DB
- Difficult disposal due to lacking rail wagons
- Probing for warfare material during construction due to suspicious points
- Renovation of 6 pcs. points
- Renovation 130 m track
- Track conversion by means of material transport and silo unit wagon at the front of the train
- 1,650 t excavated material
- Disposal of 1,550 running metres old wooden sleepers
- Installation by means of track construction train, as well as installation in the pit

VB renovation of points train station Göppingen

Customer: DB Netz AG
Construction period: 1 month Year of construction: 2021
Conversion of 10 points
Complete shutdown of the line Göppingen-Ulm from 14/08/2021 – 27/08/2021
approx. 3,500 t excavated material
approx. 3,500 t delivery of new ballast

Particularities

Difficult conditions due to delayed delivery of materials because of supply shortages. In addition to that the GDL strike. Yellow construction site together with the business unit Technik. All “yellow“ large equipment is put to use.
Track construction cranes KRC450 + KRC1200
Point tamping machine + ballast plough
LW locomotives V100
2 x road-rail-excavator

S21, PFA 1.6a; construction stage 1, connection Interregio curve, traffic infrastructure

Customer: DB Projekt Stuttgart-Ulm GmbH
Construction period: 21 months Year of construction: 2020–2022
The locations Obertürkheim, Waiblingen, holding sidings Untertürkheim and the main station are connected by means of the existing railway infrastructure
Cable duct systems, deep drains, electric energy systems, as well as new track infrastructure are installed and renovated.

Track and point renovation train station Konstanz

Cross-border track conversion

Customer: DB Netz AG, Regionalbereich Südwest
Construction period: 9 months Year of construction: 2020
Renovation 9 pcs. points
Renovation 90 m track
3,227 t excavation
Renovation level crossing Hafenstraße (Germany)
Renovation level crossing Freie Straße (Switzerland)
Shut down of level crossings was only possible during nights
Registration of all personnel with the customs authorities of Switzerland on a daily basis
Customs declaration of all construction materials and equipment
Enlistment of all vehicles in swiss railway transportation companies
Strict controls of borders due to Corona Virus