Track construction, renewal and upgrades

The extension and availability of transport lines are becoming increasingly more essential today. We solve the logistical and organizational challenges in new track construction, maintenance and renovation while keeping the route available as much as possible. As a specialist, we can handle all types of track construction from ballasted track to slab track and encompasses all track gauges from standard, to mountain, cable and narrow-gauge railways.

All projects are fully implemented from A to Z – economically, reliably, and rapidly even with non-interrupted service. Our combination of skilled managers, experienced employees, innovation, and cutting edge technology enable us to master all tasks with the utmost precision.

 

RRX PA 1.2 Leverkusen

Customer: DB Netz AG
Contruction period: 39 months Year of construction: 2020–2023

In connection with the four-track upgrade between Köln and Leverkusen 6 km of track were renovated, 17 concrete points (type 760) were installed and on a stretch of 3,000 m a fourth track newly constructed with the complete substructure and a new drainage system (deep drain, drain facilities). 1,200 m of noise protection walls needed to be dismantled, in order to make space for the new construction of noise protection walls of up to 6 m of height with a total length of 2,000 m. A total of 10,000 m cable ducts, 61 signal foundations and 300 m steel pipe crossings were installed.


9 km construction of new track / upgrade of track
17 pcs. new construction of points / conversion of points
2,000 m noise protection wall
10,000 m cable ducts
300 m crossing (steel pipes)
4,500 m construction road

Particular challenges of this project:

Work during nighttime shutdowns in the area of the ICE line
Works in connection with existing structures in the town centre of Leverkusen

Track conversion Gammertingen-Kleinengstingen

Customer: SWEG Schienenwege GmbH
Contruction period: 24 months Year of construction: 2021–2022

2021 Maintenance works:

Track renovation Mühringen 436 m track renovation with soil stabilisation and 300 m safety catch for ballast
Track renovation Laucherthal: 190 m track renovation with deep drain
Track renovation Starzeln: 796 m track renovation with soil stabilisation and cable route Signalling works
Track renovation Engstingen-Trochtelfingen: track renovation 6,500 m with soil stabilisation and cable route, 7 passages

2022 Maintenance works:

Track renovation Engstingen-Gammertingen 4,500 m:
55 t old ballast and soil excavation 29,400 t
Soil stabilisation 31,600 m²
New ballast 24,500 t
Sleepers (total) 11,279 pcs.
New rails 14,868 m
Thermit welding joints 308 pcs.
Concrete through 3,795 m
Safety catch for ballast 3,125
Track renovation Hettingen: 1,002 m track renovation with soil stabilisation, 600 m safety catch for ballast, 800 m cable route
Track renovation Seehäsle: 333 m track renovation with soil stabilisation

Bayernhafen Nuremberg track construction works

Customer: Bayernhafen GmbH & Co. KG
Contruction period: 5 months Year of construction: 2022–2023

In the surroundings of the Bayernhafen Nuremberg individual points and track sections were renovated.

Points:

Renovation of the compete points 13 and 14 with material, exchange of ballast and disposal.
Exchange of sleepers of the points 5 and 6, renovation of the set of switches with lane, sleepers with material, exchange of ballast and disposal.
Exchange of sleepers of the points 27, 47, 78, and 80, sleepers with material, exchange of ballast and disposal.

Tracks:

Track 3: exchanges of rails, 1,551 m rails
Track 2, main track 2, main track 7: new sleepers, new rails, complete renovation with material, exchange of ballast and disposal.
Track 2: 1,650 m rails, 1,238 pcs. sleepers
Main track 2: 478 m rails, 374 pcs. sleepers
Main track 7: 300 m rails, 231 pcs. sleepers
Turnout point 73a – point 85: exchange of sleepers, 218 pcs. sleepers

VB 23 Rbf Kornwestheim

Customer: DB Netz
Contruction period: 6 months Year of construction: 2023
Renovation of 18 points
Renovation of 3,320 m track including complete renovation of track bed
Renovation of 6,400 m side path

Heidenheim-Mergelstetten-Königsbronn

Customer: Deutsche Bahn AG
Contruction period: 6 months Year of construction: 2022
Railway line 4760 Aalen – Ulm.
Track renovation Heidenheim-Mergelstetten and track renovation Königsbronn track 2, incl. safety services.
1,181 m track renovation with complete renovation of track bed Heidenheim-Mergelstetten.
923 m track renovation with complete renovation of track bed Königsbronn track 2
4,150 m³ old ballast
3,780 t base ballast
2,500 t backfilling ballast

Elztalbahn

Customer: DB Netz AG
Construction period: 27 months Year of construction: 2022
6,000 m cable duct size II
50,000 m control, communication, and safety system and telecommunication technology cable laying
Full conversion of 7 level crossings incl. widening of road and signalling equipment
Conversion of the signals of two level crossings
3,500 m ballast cleaning and track conversion by means of machines
New construction of a platform at the train station Waldkirch
Production of 60 m Zwiesel platform roof
Façade renovation of the listed train station building
Adaptation of the platform at the stopping station Buchholz
Traditional track conversion 1,800 m
1x individual point - EW 300 and 1x similar flexure turnout - IBW 500
Construction of boundary path 240 m
Widening of dam 450 m
Production of scour protection
Disposal of 30,000 tons soil and stones

VB 21 Central station Freudenstadt

Track and point renovation main station Freudenstadt

Customer: Thyssen Krupp
Construction period: 3 months Year of construction: 2021
6 construction phases with different shut-down situations
Renovation of 6 points – 5 using railway crane, 1 assembled in the hole
3,750 t ballast per truck
1,500 t ballast per railway vehicle
5,400 pcs. concrete sleepers B70
4,000 m rails S49 and S54
200 m seepage water drainpipe
120 m cable ducts

Track renovation and point renovation Sindelfingen-Herrenberg

Customer: DB Netz AG
Construction period: 7 months Year of construction: 2021
Track renovation with complete track bed renovation 1,650 m
Track renovation with complete track bed renovation and formation protection layer 815 m
Point renovation of a total of 18 points incl. complete track bed renovation
6 pcs. individual points 190
5 pcs. individual points 500
1 pc. similar flexure points 300
4 pcs. similar flexure points 500
1 pc. contrary flexure points 760 by means of point transport vehicle
1 pc. simple similar flexure crossing points 500

Track renovation Hörpolding-Schalchen

Customer: DB RegioNetz Infrastruktur GmbH Südostbayernbahn
Construction period: 6 months Year of construction: 2021
9,480 m dismantling of tracks of various rail systems
9,480 m new construction of track, traditional with y-shaped steel sleepers
12,000 m³ dismantling of track bed partly by using machines and preparation for disposal
10,000 m³ installation of track ballast partly by using machines
7,500 pcs. storage of sleepers
19,000 m unloading of rails from railway vehicles and installation of rails
206 pcs. thermit welding of joints
12,000 running metres production of side paths and shunting tracks
20 pcs. demolition and reconstruction of level crossings

Track renovation with dam restoration Mündling-Otting

Customer: DB Netz AG – Produktionsdurchführung (Production Administration) Augsburg
Construction period: 14 months Year of construction: 2020
2,400 m track dismantling/new construction with two rails on one sleeper
22,800 m³ deep soil stabilisation by means of the milling, mixing, injection method
5,900 t cement for deep soil stabilisation
900 m production of supporting wedge for stabilisation of the dam abutment
8,000 m³ slope stabilisation by producing soil cement supports using the hydro cementation method
1,600 m³ soil stabilisation by means of the lime cement method
3,500 m³ production of protection and base course
7,000 m³ removal of (old) track ballast
6,500 m³ installation of track ballast (new)
4,000 m³ soil removal
800 m production of deep drains
35,000 t disposal of soil
1 pc. track crossing DN 300
3 pcs. production of signal foundations by means of driven casing pipes

Hochbahn, Duisburg

Installation of ballast over Telebelt and installation of track sections

Customer: Thyssen Krupp
Construction period: 1 week Year of construction: 2019
Construction period from 16/09/19 – 21/09/2019, every day 2 x 10 hrs
Installation of 2,300 t ballast, compacted in layers, 5 layers
Installation of track sections, 3 tracks, length approx. 36 m each
Difference in height: 7.2 m