We perform all welding work on track materials and components using all processes - for operational tracks of Deutsche Bahn AG (performed pursuant to Guideline 826.2050. I), non-federal railways and transport companies.

Aluminothermic fusion welding (AS-SKV process) in tracks and switches
Arc welding in the E/MF process
Arc welding on track components in the E/MF process
Creation of insulated joints of the MT type
Building up by arc welding of switches (common crossings) and tracks

We also perform the following services:

Construction management for the execution of stress equalization in continuous welded rails/switches pursuant to Guideline 826.2050
Unloading of long welded rails from flat wagons of up to 180 m in length with our EMD-type long rail unloading equipment
Loading and unloading of rails of up to 60 m in length from public rail wagons with the CR rail handling equipment

Station Günzburg

Customer: Vitus Rieder GmbH
Construction period: August 2019–December 2020 (Framework contract)
Year of construction:
09/2019

Approx. 30 welding joints

Shunting yard Esslingen

Customer: Deutsche Bahn AG
Construction period: May 2019–November 2019 (Framework contract)
Year of construction:
06/2019

3,400 m unloading of rails

Frankfurt am Main - Kelsterbach

Customer: DB Netz AG
Construction period: June 2019–December 2019 (Framework contract)
Year of construction:
09/2019

Approx. 110 welding joints

Company site Cologne Düsseldorf Oberraden Duisburg Mönchengladbach

Customer: DB Netz AG
Construction period: 22 months
Year of construction:
2017–2018

150 switch blades and frogs after use of large construction machines
80 points with system Profilia

Joint venture AVI LW-Sinzig

Customer: DB Netz AG
Construction period: August 2017–December 2025 (Framework contract)
Year of construction:
2017–2025

Superstructure welding tracks and points, processing of rails